Guyana's Prime Minister Mark Phillips has confirmed that the government approved additional financing of more than US$100 million for Lindsayca, the contractor building the Wales Gas-to-Energy (GTE) project. Kaieteur News, in an article dated 12 November, says he confirmed it at Wednesday's sitting of the National Assembly (the paper does not give the date; the Wednesday before publication was 11 November) and in an interview with the paper. "Yes we had meetings and we approved additional financing," Phillips told Kaieteur News. He could not recall the exact sum. United News in Paramaribo relayed the report on 12 November. Kaieteur had earlier reported that the US Embassy in Georgetown was allegedly pressing the government for US$102 million.
It is a Guyanese story, but it lands squarely in Suriname's lap. Suriname's own first gas development, the Sloanea field in Block 52, shares a similar logic: offshore gas, a heavy infrastructure chain, and a promise of new value for the economy. Guyana's version has already run into trouble, and Paramaribo can study how.

What Guyana has just agreed to pay
The Wales project was initially due for completion by the end of 2024. The original contract was US$759 million, according to Kaieteur News. In May 2026, Demerara Waves reported a settlement of about US$97.2 million with the contractor over soil-stabilisation and delay-related claims, taking the cost of the plants to about US$856 million. The new financing comes on top of that settlement. Kaieteur also reports close to US$2 million in legal costs for the dispute.
The latest commitment, which Kaieteur says the government cited in August, is first power of 57 MW by December 2026. Asked about delivery, Public Utilities and Aviation Minister Deodat Indar was quoted as saying: "The original commitment is that you have to deliver one of the turbines by December." He added that the government receives weekly progress reports from the company. Kaieteur says the project is likely to miss another deadline, but it does not report a confirmed new completion date.
The project also depends on gas from offshore. Kaieteur reports that the 220 km pipeline carrying gas from the Liza fields in the Stabroek block to shore was built by ExxonMobil, was completed in December 2024 and is now under repair. ExxonMobil has not disclosed the repair costs, so the final price remains unknown.
The cost of waiting
Guyana has been bridging the gap with imported fuel and rented generation. Kaieteur News reports that heavy fuel oil imports since 2024 are expected to cost at least US$619 million, and that two Turkish powerships are rented at G$126 million per day, a figure it attributes to opposition figure David Patterson. The promised cut in electricity bills has not materialised, because the plant is not yet running.
Kaieteur also cites a figure of US$984 million as the additional cost it expects the delays to cause, but the article does not show how that figure is built. Treat it as indicative only.
The lesson is the arithmetic of delay: when a gas-to-power project slips, the bill does not pause. It keeps arriving as fuel imports and rentals, and it arrives before any cheap-power benefit does.
Where Suriname's gas stands
On 11 November 2025 Staatsolie approved the commercial field for the Sloanea-1 gas discovery in Block 52 (announced on 13 November 2025). Petronas Suriname is operator with 80%, and Staatsolie subsidiary Paradise Oil Company holds 20%. Staatsolie said a final investment decision (FID) was planned for the second half of 2026, after Petronas Suriname submits a Development Plan for Staatsolie's approval, with first gas expected in 2030. The selected concept includes gas development wells, subsea infrastructure and a floating LNG facility, which Staatsolie called a first in the region. I found no announcement of an FID as of 14 November in the sources I checked, so the decision remains, on the public record, pending.
Note the difference in design. Guyana's gas is piped ashore to feed a power plant. Sloanea is described by Staatsolie as a floating LNG development, and the sources I checked do not say how much gas, if any, would be reserved for domestic use. Suriname's domestic power question, which wimpel.online has examined before, is therefore not automatically solved by Sloanea; it depends on volumes and terms that have not been made public in those sources.
Three questions for Paramaribo
- Who carries interface risk? Guyana's plant depends on a pipeline built by a different party from the plant contractor. Any Surinamese domestic gas scheme needs contractual clarity on who pays when upstream and downstream schedules diverge.
- What is the fallback bill? Before FID, the state should publish what bridging power would cost if first gas arrives later than 2030.
- Is domestic gas in the deal? Staatsolie says monetisation options for the Block 52 gas were assessed under the production sharing contract, leading to a gas addendum. Whether that framework allocates volumes for local power and industry is a policy question that is easier to settle now than after FID.
The verdict
None of this says Sloanea will fail; Staatsolie has announced the commercial-field approval and a planned FID, and the project is still at an early stage. But Guyana shows that gas-to-power is a project-management problem as much as a geology one, and that the real price of delay is paid by consumers and treasuries long before the first molecule flows. Suriname has roughly four years and one FID to learn from Wales. It should use them.
Sources & further reading
- Kaieteur News, 12 November 2026: Govt hands Lindsayca more than US$100M to complete troubled Wales gas project
- United News (citing Kaieteur News), 12 November 2026: Guyana pompt ruim 100 miljoen dollar extra in vertraagd gasproject Wales
- Demerara Waves, 14 May 2026: Soil stabilisation dispute settlement raises cost of Wales plants by almost US$100 million
- Staatsolie: Commercial Field approved for Sloanea-1 gas discovery in Block 52
- Staatsolie: year-end review 2025
- Blackouts in an Oil Nation: Why Suriname's Gas Clock Matters